Winchburgh M9 Junction, West Lothian
- RJ Mcleod
- Jun 1, 2022
- 1 min read
Updated: Jun 12, 2025
All Photos by 'Gary Barker Photography'
Client: Winchburgh Developments Ltd
We were Principal Contractor on this project for the construction of a new dumbbell grade-separated junction with 4 no. new slip roads. The project consisted of site clearance, earthworks, ground improvements, drainage including SUDS and detention basins, road construction, footway, lighting, Intelligent Transportation System (ITS), CCTV, PU diversions, Vehicle Restraint Systems (VRS), environmental measures, landscaping and accommodation works.
Principal Elements
Excavation/deposition 120,000m3
Ducting 10,700m
Topsoil strip/deposition 30,000m3
Stormwater drainage 6,000m
Imported Class 1 material 232,000m3
Manholes/catchpits 150 no.
LECA lightweight fill 9,140m3
Pre-cast concrete portal frame culvert 1 no.
Capping (6F5) 17,500m3
Kerbing 3,800m
Type 1 sub-base 8,500m3
Surfacing 23,500m2
Points of Interest
Approximately 8000m3 of Leca lightweight fill is incorporated into two of the junction embankments. The material was delivered from Portugal to the Port of Leith and delivered to site in a ‘just in time’ format to minimise to environmental impact.
No material was removed offsite as part of the dig out/replacement works – instead it was incorporated into landscape and amenity bunds to the south west of the new junction.
Many of the structural embankments on the scheme were formed using a waste product from the historical oil shale mining which was prevalent in West Lothian between 1851 and 1963. The material from Niddry Bing approximately 1.5km from the junction was used.
The junction provides direct access to the Category A listed and Scheduled Monument, Duntarvie Castle.
Challenging ground conditions (soft lacustrine deposits) requiring up to 4m deep excavation at the toe of existing 10-11m high M9 motorway embankment




