Uig Harbour Redevelopment, Isle of Skye
- 2 days ago
- 1 min read
Client: The Highland Council
The project comprised the redevelopment of Uig Harbour to upgrade the existing ferry terminal with new infrastructure, improving the ferry service and provide a safer, enhanced experience for all users.
RJ McLeod was appointed as Principal Contractor to deliver the works, which included foreshore reclamation, piling for the new terminal building foundations and widening of the approach way structure by 6m through the construction of an open tubular steel piled precast and /in situ concrete suspended deck.
The pierhead was partially demolished and reinstated, with the existing dolphins replaced by new structures. The works also included construction of a new bankseat and linkspan, widening of the berthing structure by 16m using a solid steel piled in situ concrete structure, installation of new fenderline piles, fender units and pier furniture, resurfacing of the existing marshalling and reclamation areas, repairs to existing concrete and installation of new services.
Principal Elements
Dredging 30,200m3
Quarry materials 172,600t
Concrete 5,700m3
Precast 2,330t
Piling 3,384t
Resurfacing 6,512t
Points of Interest
Harbour remained operational throughout the project, maintaining access for fishing vessels and pleasure boats with the Western Isle Ferry berthing 3 times a day
Planned outage undertaken between September 2022 and February 2023 to facilitate replacement of the dolphins and linkspan
Remote location requiring careful planning of logistics, material deliveries and storage
Complex temporary works designed and implemented to facilitate construction
Delivery within a confined working environment






