Mallaig Overnight Ferry Berth

Oct 13
1 min read

Updated: 6 days ago


Client: Mallaig Harbour Authority

The project included the upgrade of an existing pier at Mallaig Harbour, with works undertaken while maintaining ongoing ferry operations.

 

The scope included the temporary diversion of shore power, water and navigation lighting, demolition of the existing wave wall and installation of a new sheet pile wall. Works also included excavation of the existing cellular cofferdam to install ties and construct concrete anchor blocks, infilling between existing cells, construction of a new concrete deck slab and installation of associated services and quayside furniture.

Principal Elements

  • Sheet piles - 175T

  • King posts - 80T

  • Rock fill - 1,300T

  • Concrete slabs - 425m3

  • Concrete anchor blocks - 420m3

  • Scour hole infill - 1,500T

  • Pneumatic fenders -13


Points of Interest

  • Works delivered within an operational harbour while maintaining ferry operations

  • Tight programme delivered during challenging winter weather conditions

  • Unforeseen ground conditions required a change to the piling installation methodology

  • A large scour hole discovered at the ferry berth was infilled without disruption to ferry sailings

  • Coordination of multiple specialist subcontractors throughout the works