Kyleakin Marine Works

  • RJ Mcleod
  • Jun 14, 2018
  • 1 min read

Updated: Jun 12


Client: Marine Harvest Scotland Ltd

The works, to encase and extend the existing finger pier, consisted of the following: combi piling and dredging, transit and installation of two number caisson onto prepared bed at -10m Chart Datum, construction of 10,200m2 insitu concrete deck, laydown area and slipway and placement of 8,000m3 of rock armour imported by sea.

Principal Elements

  • Infill works 120,000 tons

  • Rock armour 22,500 tons

  • Combi piling walls 214m

  • Sheet piling walls 240m

  • Bearing piles 20 no.

  • Concrete 7,500m3

  • Rebar 700 tons

  • Fenders 12 no.

  • Dredging 85,000m3

  • Sea bed armour 1,500m3

  • Underwater concrete 200m3

  • Caisson foundations 2,000m3

  • Drainage 400m

  • Slipway construction 900m2

Points of Interest

  • Caissons (2 no., each 30m long x 20m wide x 15m high) constructed at Corpach and towed to Kyleakin by tug

  • Marine Mammal Observation and Passive Acoustic Monitoring works for marine mammal protection

  • Completed within a marine protected area