Ardrossan North Shore Enabling Works

Oct 9
1 min read

Client: North Ayrshire Council

The Ardrossan North Shore Enabling Works supported the redevelopment of the former Ardrossan North Shore site, facilitating the future construction of an educational campus alongside further residential and commercial development as part of the wider Ardrossan regeneration programme.

 

The scope included extensive earthworks, construction of a coastal rock armour revetment and coastal path, road and parking infrastructure, and the installation of utilities and drainage

Principal Elements

  • Earthworks cut/fill - 60,000m3 

  • Foul and surface water drainage - 2,450m (150mm-750mm Ø)

  • Capping import - 250,000T

  • Rock armour import - 72,000T

  • RC retaining wall - 800m

  • Carriageway and footway surfacing - 17,500m2


Points of Interest

  • Tidal working required for construction of the coastal rock armour revetment

  • Works delivered alongside residential and commercial properties

  • Significant community benefits delivered including 5,378 hours of training Work experience placements, taster days, STEM events and an Undergraduate Mentoring Scheme provided

  • Educational engagement with more than 1,000 pupils from local schools

  • 80% of suppliers used were based within 40 miles of the site

  • Over 41,000 tCO2e carbon saving achieved through sourcing 75,000 tonnes of rock locally