Streetscaping/Environmental Improvements

Perth High Street

Client
Perth & Kinross Council
Value
£1.33M
Architect
Perth & Kinross Council
Programme
44 Weeks
Contract Form
Measure & Value
Completed
2011


The contract was for public realm improvements to Perth's main shopping area, delivered in 4 phases with final completion taking place 2 weeks early, to improve the underlying structure of the street as well as enhancing the aesthetics of the area. It included the excavation and construction of concrete road slab, installation of granite paving and kerbing, gullies, 'Envirodrain' drainage channel, new covers, street furniture and tree pits.

Principal Elements included: Granite Kerb 400m / Drainage Channel 500m / Granite Paving 6,000m2 / Gullies 42 no. / New Covers 80 no. / Concrete Road Slab 500m3 / Excavation 1,000m2

 

 

Key Issues:

  • Public thoroughfare and access to local premises maintained at all times
  • Substantial interface with both public and shopkeepers