Head Office/Registered Office

2411 London Road
Glasgow
G32 8XT

Tel: 0141 764 2411
Fax: 0141 764 2434

 

North Office
Strathpeffer Road
Dingwall
IV15 9XB

Tel: 01349 860000
Fax: 01349 860005

Peterhead 1.jpg whitespacer.jpg Peterhead.jpg
Marine & Waterways

Smith Embankment Development, Peterhead

Client
Peterhead Port Authority
Value
JV £27.15M, RJM Portion £14.00M
Engineer
Peter Fraenkel & Partners
Programme
84 Weeks
Contract Form
Modified ICE 7th Edition
Completed
2010

 

The contract, for a new quay and breakwater, was carried out as a Joint Venture, with Westminster Dredging responsible for dredging and rock armour works.

 

The initial brief was for the design and construction of two lengths of new quay involving suspended decks over rock armour revetments so as not to have a detrimental effect on the wave regime within the harbour. All the initial tender returns were over budget. The Client's Engineer then developed a structural scheme of a composite steel / precast concrete beam / insitu concrete topping suspended deck supported on monopiles cored into bedrock at the sea end and sitting on an insitu concrete bankseat at the shore. The solution, which is more akin to bridge construction than a traditional marine deck, was re-bid by the Joint Venture working with a specialist subcontractor and satisfied the design and budget requirements allowing a price to be agreed and the project to proceed.

 

RJ McLeod's workscope on this contract comprised the construction of a 120m long, 22m span, open piled quay. A specified load of 500 tonnes at 20m lift radius was required at the heavy lift area. Also included was a remote mooring dolphin together with associated paving, drainage and services provision.

 

 

Principal Elements included:

Marine Piles 19 no. (1.4m dia.) drilled 10m into seabed

Structural steelwork 780T

Reinforced concrete 5,500m3

Precast pre-stressed concrete beams 400 no.

Mechanical and electrical quayside services
  

 

Key Issues:

  • Works carried out within a busy harbour environment - close liaison with harbour authorities required to ensure minimum disruption to normal habour operations
  • Contractor-designed mechanical and electrical services with design development ongoing