| Client |
Scottish Power Generation Ltd |
| Value |
£2.80M |
| Designer |
Jacobs |
| Programme |
32 Weeks |
| Contract Form |
ICE 7th (Amended) |
| Completed |
2009 |
The project is for the construction of a building platform for the new Biomass Power Plant. This involves the import from the adjacent power station of 200,000t of PFA fill. Also included is the construction of a new access roundabout and road along with associated drainage and band drains. The provision of services for new facility and rearranging of existing facilities at gatehouse is also part of the scope. A drainage ditch was diverted as part of the contract, under a SEPA CAR licence.
Principal Elements included:
Class 6C Material 32,000t / Class 1A Material 26,000t
Type 1 Material 2,200t / Class 6F2 Material 2,000t
Topsoil 6,000t / Concrete 400m3
Polyfelt Geotextile 82,000m2
PFA/FBA 100,000m3 / Surfacing Material 4,460m2
Key Issues: