Energy

Gordonbush Wind Farm

Client
SSE Generation Ltd
Value
£9.55M
Consultant
Grontmij
Programme
63 Weeks
Contract Form
NEC 3 Options A
Completed

2011

 


This contract was for the Design and Construction of a 35 no. turbine wind farm on a heavily peated site approximately 6 miles west of Brora. It included the construction of roads, hardstandings and substation hardstanding. A welfare building was constructed as part of the project, 3 no. met masts erected and a single track 'C' class road upgraded.

 

Principal Elements include: Roads (new) 22,200m / Roads (upgraded) 12,000m / Hardstandings 40,000m2 / Substation Hardstandings 8,000m2 / Met Masts 3 no. 

 

 

Key Issues:

  • Very heavily peated site
  • All rock won from 3 onsite borrow pits
  • Environmentally sensitive area
  • Onsite batching plant
  • Tight programme