West Sands 1.jpg whitespacer.jpg West Sands.jpg
Roads and Structures

West Sands, St Andrews

Client
Fife Council
Value
£0.88M
Engineer
Fife Council
Programme
24 Weeks
Contract Form
Measure and Value
Completed
2009

 

The project consisted of a new access road, bus turning and parking facilities and upgrading of the existing car park to accommodate 240 parking spaces. 1,200m of existing carriageway was reconstructed using modern recycling processes. Included within the project is an 850m diversion of a 63mm diameter water main.

 

The St Andrews Links Trust and the R&A were co-funders on the project and a key concern was the potential disruption of the high-profile Dunhill Cup. Through close co-operation and careful programming, the main works were completed early to avoid disruption.

 

 

Principal Elements included: Surfacing 6,500m2 / Drainage 700m /

Water Main 850m diversion

 

 

 

Key Issues: 

  • Main works completed early for the start of the high-profile Dunhill Cup
  • Early and continued close liaison required with the land owners, the Links Trust
  • Work immediately adjacent to the environmentally-sensitive St Andrews sand dunes and golf courses