Earlsburn Wind Farm
Client
|
Falck Renewables
|
Turnkey Contractor
|
Nordex UK Ltd
|
|
Size
|
15 x 2.6MW
|
|
Programme
|
27 Weeks (completed 2006)
|
Contract Form
|
Lump Sum
|
| |
|
The contract is for the construction of a hill access track including two river bridge crossings. Wind turbine reinforced concrete foundations were constructed with the concrete for each foundation produced by an on-site batching plant. Rock for general fill material, processing into road stone and for concrete aggregates was won from an on site rock borrow pit which was then landscaped when the project was complete. A control building was constructed and road improvements on the main roads (eventually used to access the site) were carried out.
Principal Elements included:
Hill Access Track 10,000m
Wind Turbine Reinforced Concrete Foundations 15 x 350m3
Key Issues:
- Working in an area of environmental and archaeological sensitivity requiring presence of ecological Clerk of Works to monitor activities
- Working around and across a river which is an SSSI and a feeder to the Denny water supply.